ASTUTE CLASS SUBMARINE


The '''Astute'' class submarines' are the next generation nuclear Fleet submarines of the Royal Navy. When completed, the boats will set a new standard for the Royal Navy in terms of weapons load, stealth and comfort for the crew. The boats are being constructed by BAE Systems at Barrow-in-Furness.

Contents
Background
History
Contract award
Delays
Further orders
Boats
General characteristics
External links
References

Background


As the ''Swiftsure''-class submarines aged, the Royal Navy began to design their replacements. The original design called for large submarines designed for blue-water operations. Feasibility studies began in 1986 and were completed by 1989. A design contract was placed with Vickers Shipbuilding and Engineering Ltd. (VSEL) in 1987, but with the end of the Cold War the project was cancelled in 1992. Emphasis switched to the production of a second batch of ''Trafalgar''-class submarines (''Batch 2 Trafalgar Class'' or B2TC). However the development was extremely slow and initial tenders received from VSEL in June 1995 were too expensive.
Meanwhile, the Royal Navy has changed its submarine-employment strategy from the Cold War emphasis on anti-submarine warfare to the concept of "Maritime Contributions to Joint Operations." The proposed replacement boats were redesigned; the primary mission of the ''Astute'' class became direct support of surface forces.
Original plans were for seven boats of the ''Astute'' class to replace five ''Swiftsure''-class submarines (''Sovereign'', ''Superb'', ''Sceptre'', ''Spartan'', and ''Splendid'') and the two oldest ''Trafalgar''-class boats (''Trafalgar'' and ''Turbulent''). Plans, however, have been scaled back. The ''Swiftsure''-class will be entirely decommissioned by 2010, when only the first of the Astute-class will be coming into service. HMS ''Trafalgar'' is to be decommissioned in 2008, followed by HMS ''Turbulent'' in 2011.

History


Contract award

On March 17, 1997, The Ministry of Defence announced that it was to place a £2 billion order for three submarines and further that they would be called the Astute class. On March 26, 1997, the contract was signed with GEC-Marconi Limited for the first three boats: ''Astute'', ''Ambush'' and ''Artful''. These names were last given to ''Amphion''-class submarines that entered service towards the end of World War II. GEC would build the submarines at its VSEL subsidiary (now BAE Systems Submarines).
''Astute''-class boats will be powered by a Rolls-Royce PWR2 reactor and fitted with a pump-jet propulsor. The PWR2 reactor was developed for ''Vanguard''-class ballistic missile submarines. As a result ''Astute''-class boats are about 30 per cent larger than previous British attack submarines, which were powered by smaller reactors. It will be the first Royal Navy submarine class to have a bunk for each member of the ship's company, ending the practice of 'hot bunking', whereby two sailors on opposite watches shared the same bunk.
Like all Royal Navy submarines, the fin of the ''Astute''-class boats will be reinforced to allow surfacing through ice caps. They can fire Tomahawk cruise missiles from their launch tubes, including the new "tactical Tomahawk" currently under development. More than 39,000 acoustic tiles will mask the vessel's sonar signature, giving the ''Astute'' class a better stealth quality than any other submarine previously operated by the Royal Navy. The vessel is equipped with the advanced 2076 Sonar System, which is capable of identifying and tracking vessels across thousands of square miles of ocean. According to the MOD around 5,500 people are presently employed in the Astute building programme.
Delays

The ''Astute'' class was expected to be built roughly 20% quicker than earlier boats, with lower running costs and a much smaller ship’s company. However, the programme's progress has slipped by 4 years and has a predicted cost overrun of £1 billion,[1] and required a U.S. engineering management team from General Dynamics Electric Boat to be brought in to resolve programme problems.[2] The UK House of Commons Defence Committee, in July 2004, estimated the cost of Astute as £3,498 million compared to £2,578 million approved at Main Gate.[3] Furthermore they noted that the predicted in-service date was January 2009 compared to the date of June 2005 approved at Main Gate. A £164 million cost increase was disclosed in a National Audit Office report in November 2006. However the NAO noted the in-service date was then ahead of schedule compared to the revised in-service date.[4]
BAE Systems has indicated that the Astute submarine project has maintained its improved performance, and first-of-class ''HMS Astute'' was launched by Camilla, The Duchess of Cornwall on 8 June 2007.[5] Work on the second submarine, ''Ambush'', is also proceeding well with major milestones such as the closure of the reactor compartment, demonstrating significant schedule advance compared with Astute. BAE and the MoD have made efforts to reduce costs and achieved significant cost-cutting and productivity gains.
Further orders

As of 28 August 2006 BAE are currently negotiating for a contract to build another four Astute class submarines.[6] British Armed Forces Minister, Adam Ingram, has announced a further advance in the Astute Class submarine programme, with preparations for a further SSN underway. The Minister told MPs:
BAE Systems Submarines had ordered long-lead items for a fourth boat in August 2006. In March 2007, DefenseNews.com reported that a final price for boats 2 & 3 had been reached.[7] The fourth boat was ordered on 21 May 2007 and it was announced that she is to be called ''Audacious.''[8]

Boats


Name Pennant number Laid down Launched Commissioned
''Astute'' S119 31 January 2001 8 June 2007[9] 2009
''Ambush'' S120 22 October 2003 ? 2010
''Artful'' S121 11 March 2005 ? 2012
''Audacious'' S122 Late 2007 ? ?

General characteristics



★ Sensors:


Thales Underwater Systems Sonar 2076


Atlas Hydrographic DESO 25 depth-finding echosounder


★ Two Thales Optronics CM010 periscopes


Raytheon Systems Ltd Successor IFF system

External links



Royal Navy official site

Photos from the roll out / launch (BBC)

ThisIsLondon article "Britain launches massive submarine that can hear a ship from across the Atlantic" (June 8th, 2007)

Navy Matters - Astute Class

References


1. Public Accounts - Forty-Third Report Committee of Public Accounts
2. US team to work on submarine order
3. Progress on key projects
4. Royal Navy's weapons projects affected by delays and cost troubles James Boxell
5. New UK nuclear submarine launched
6. New nuclear sub is lifeline for Barrow
7. U.K., BAE Agree on Nuclear Submarine Costs
8. Royal Navy to Get New Attack Submarine
9. New UK nuclear submarine launched


This article provided by Wikipedia. To edit the contents of this article, click here for original source.

psst.. try this: add to faves