PROJECT PLANNING
'Project planning' is part of project management, which relates to the use of schedules such as Gantt charts to plan and subsequently report progress within the project environment.[1]
Initially, the project scope is defined and the appropriate methods for completing the project are determined. Following this step, the durations for the various tasks necessary to complete the work are listed and grouped into a work breakdown structure. The logical dependencies between tasks are defined using an activity network diagram that enables identification of the critical path. Float or slack time in the schedule can be calculated using project management software[2]. Then the necessary resources can be estimated and costs for each activity can be allocated to each resource, giving the total project cost. At this stage, the project plan may be optimized to achieve the appropriate balance between resource usage and project duration to comply with the project objectives. Once established and agreed, the plan becomes what is known as the baseline. Progress will be measured against the baseline throughout the life of the project. Analyzing progress compared to the baseline is known as earned value management.[3]
★ Cost overrun
★ Dependency Structure Matrix
★ Kitchen sink syndrome
★ Megaprojects
★ Project Management Institute
★ Prince2
1. Project Management: A Systems Approach to Planning, Scheduling, and Controlling, Harold Kerzner, , , Wiley, 2003, ISBN 0-471-22577-0
2. Software Engineering Project Management, Richard H. Thayer, Edward Yourdon, , , Wiley-IEEE Computer Society Press, 2000, ISBN 0-8186-8000-8
3. Earned Value Project Management, , Quentin, Fleming, Project Management Institute, 2005, ISBN 1-930699-89-1
★ International Project Management Association
★ Project Management Association of America
★ Project Management Institute
★ Planning Engineers Organization
★ Association for Project Managers (UK)
★ Prince2 site from OGC (UK Office of Government Commerce)
Initially, the project scope is defined and the appropriate methods for completing the project are determined. Following this step, the durations for the various tasks necessary to complete the work are listed and grouped into a work breakdown structure. The logical dependencies between tasks are defined using an activity network diagram that enables identification of the critical path. Float or slack time in the schedule can be calculated using project management software[2]. Then the necessary resources can be estimated and costs for each activity can be allocated to each resource, giving the total project cost. At this stage, the project plan may be optimized to achieve the appropriate balance between resource usage and project duration to comply with the project objectives. Once established and agreed, the plan becomes what is known as the baseline. Progress will be measured against the baseline throughout the life of the project. Analyzing progress compared to the baseline is known as earned value management.[3]
| Contents |
| See also |
| References |
| External links |
See also
★ Cost overrun
★ Dependency Structure Matrix
★ Kitchen sink syndrome
★ Megaprojects
★ Project Management Institute
★ Prince2
References
1. Project Management: A Systems Approach to Planning, Scheduling, and Controlling, Harold Kerzner, , , Wiley, 2003, ISBN 0-471-22577-0
2. Software Engineering Project Management, Richard H. Thayer, Edward Yourdon, , , Wiley-IEEE Computer Society Press, 2000, ISBN 0-8186-8000-8
3. Earned Value Project Management, , Quentin, Fleming, Project Management Institute, 2005, ISBN 1-930699-89-1
External links
★ International Project Management Association
★ Project Management Association of America
★ Project Management Institute
★ Planning Engineers Organization
★ Association for Project Managers (UK)
★ Prince2 site from OGC (UK Office of Government Commerce)
This article provided by Wikipedia. To edit the contents of this article, click here for original source.
psst.. try this: add to faves

العربية
中国
Français
Deutsch
Ελληνική
हिन्दी
Italiano
日本語
Português
Русский
Español